Scope of Work & Supply

Trans Adriatic Pipeline is a natural gas pipeline proposed in 2003, constructed in 2016, and operational since 2020, from Azerbaijan at the Caspian Sea to Europe from Greece through Albania and the Adriatic Sea to Italy. It is a European section of the Southern Gas Corridor. As of 2022 capacity is 10 bcm per year.

Semac Construction's scope of work & supply was the Civil, Mechanical, Electrical & Instrumentation Works for BVS 9,10 & GCS 01.
Also the Engineering & Fabrication of 3 Launchers, 3 Receivers & 22 Hydrotest Heads.

January 2020

End Date

August 22, 2017

Start Date

Oil & Gas

Category

Trans Adriatic Pipeline A.G.

End Client

Bonatti - J&P JV Srl

Client

Location

North Greece

Project Info

Trans Adriatic Pipeline

- Civil, Mechanical, Electrical & Instrumentation Works for BVS 9,10 & GCS 01
- Engineering & Fabrication of 3 Launchers, 3 Receivers & 22 Hydro-test Heads